Applying statutory requirements when drafting and negotiating construction contracts throws up common problems and disputes. We cover HGCRA 1996 requirements plus other issues lke retention, set off, and escrow.
In-depth guidance and precedent documents for enforcing and challenging the adjudicator’s decision. From correcting errors under the slip rule, to grounds for a jurisdictional challenge, this is the place to go.
We publish JCT 2016 contracts and FIDIC contracts, and have related schedules of amendments for key forms. See other schedules of amendments, practice notes, and checklists for forms including NEC, MF/1, ICC.
Understand the connection between the agreements you’re advising on and what happens on the ground. Know when to push a point or let it go, and give your clients advice they can work with from design to build and beyond.
This week's edition of Construction weekly highlights includes a case in which the Technology and Construction Court (TCC) ruled on the interpretation...
Construction analysis: The Technology and Construction Court (TCC) considered the interpretation of a JCT Design and Build Contract 2016 which...
The Construction Leadership Council (CLC), in collaboration with the Building Safety Regulator (BSR) and other key bodies, has published an advisory...
The Office for National Statistics (ONS) has published data, indicating a 0.2% decrease in construction output for January 2025. This was attributed...
This week's edition of Construction weekly highlights includes an analysis of the Joint Contracts Tribunal (JCT)’s 2024 Management Building Contract...
Energy performance certificates (EPCs)—energy assessor accreditation and energy assessmentsAn energy performance certificate (EPC) gives a property an...
Executing deeds and documents in property transactions—charitiesIncorporated v unincorporated charitiesThere are currently a number of incorporated or...
Construction horizon scannerThis horizon scanner, formerly known as the ‘Construction future developments tracker’, identifies key upcoming changes...
Landfill disposals tax (Wales)What is landfill disposals tax?Landfill disposals tax is an environmental tax administrated by the Welsh Revenue...
Active bribery, passive bribery and bribing foreign public officialsThe Bribery Act 2010 (BA 2010) criminalises:•bribing another person (active...
Schedule of Amendments to JCT Minor Works Building Contract with contractor’s design 2024Schedule of amendments to the jct minor works building...
JCT Design and Build Sub-Contract 2016—Form of Agreement and AmendmentsAgreement in relation to [insert brief details of the works/project] at [insert...
Letter of instruction for expert in construction disputeNote:•this Practice Note gives specific guidance on matters proceeding in the Technology and...
Notice of AdjudicationIN THE MATTER OF THE HOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996AND IN THE MATTER OF AN ADJUDICATION[And pursuant to...
Schedule of Amendments to JCT Standard Building Contract With Approximate Quantities 2016The contract comprises the completed Standard Building...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
Escrow accounts and escrow agreementsThis Practice Note examines why parties involved in a construction project may enter into an escrow agreement (or...
Defects liability period and rectification of defectsIt is common in construction projects for defects to manifest or appear in the works. Most...
What is practical completion?Practical completion marks the end of the construction period of a project, when the works are 'finished' and the...
Build Operate Transfer (BOT) contractsThe Public Private Partnership (PPP) models are a popular way for governments to involve private investment,...
Differences between adjudication and other forms of dispute resolutionThis Practice Note identifies some of the key differences between adjudication...
Liquidated damages in construction contractsThis Practice Note explains what liquidated and ascertained damages (LADs/LDs) are and their purpose in a...
Time at large in construction contractsThis Practice Note examines the concept of ‘time at large’ in relation to the completion of works under a...
Provisional sumsWhat are provisional sums?There is no precise standard definition of provisional sum but it is generally understood to refer to an...
Scott Schedules in construction disputesScott Schedules are often very useful in construction disputes. They help to identify the key issues between...
The final account in construction and engineering contractsWhat is the final account?The expression 'final account' refers to the consolidated...
Fluctuations in construction contractsWhat are fluctuations?Fluctuations provisions are clauses in construction contracts that allow the contract sum...
Breach of natural justice in adjudicationProduced in association with 4 Pump CourtPrinciples of natural justiceIf an adjudicator breaches the rules of...
New home warrantiesThis Practice Note looks at the principal types of policy or guarantee (other than latent defects insurance) that are currently on...
Extensions of time under construction contractsThis Practice Note examines the circumstances in which a construction contract might entitle a...
Association for Consultancy and Engineering (ACE)
The physical conditions on or under the Site and its near surrounds, including artificial things and latent conditions, but excluding weather conditions.
Where the employer takes the responsibility for design and the contractor carries out the works.