Applying statutory requirements when drafting and negotiating construction contracts throws up common problems and disputes. We cover HGCRA 1996 requirements plus other issues lke retention, set off, and escrow.
In-depth guidance and precedent documents for enforcing and challenging the adjudicator’s decision. From correcting errors under the slip rule, to grounds for a jurisdictional challenge, this is the place to go.
We publish JCT 2016 contracts and FIDIC contracts, and have related schedules of amendments for key forms. See other schedules of amendments, practice notes, and checklists for forms including NEC, MF/1, ICC.
Understand the connection between the agreements you’re advising on and what happens on the ground. Know when to push a point or let it go, and give your clients advice they can work with from design to build and beyond.
The Construction Leadership Council (CLC), in collaboration with nima, has launched an Information Management Initiative (IMI), designed to transform...
Construction analysis: This case considered the law of prescription—specifically when the prescriptive period ought to begin in a case of latent...
Dispute Resolution analysis: The claimant, a former member of parliament, sued the defendant for damage to his reputation as a result of alleged...
The Royal Institution of Chartered Surveyors (RICS) has published its latest UK Construction Monitor for the third quarter (Q3) of 2024, highlighting...
This week's edition of Construction weekly highlights includes a case where the Inner House of the Court of Session held that compliance with notice...
Assignment by a funder in construction projectsBanks and other funders frequently take an assignment of the benefit of the suite of construction...
Assignment in construction contractsThis Practice Note looks at why assignment of rights is an important issue in construction and when parties might...
Performance bonds—construction projectsThis Practice Note examines the nature of performance bonds, why they are required and where they fit into the...
On demand performance bonds—construction projectsIntroductionThe purpose of this Practice Note is to:•examine the nature of the on demand performance...
Claims for rectificationThis Practice Note outlines when a claim for rectification may be appropriate, what you need to establish to succeed on such a...
Interest on late payment clause1Interest on late paymentIf either party fails to make payment in accordance with this Agreement the other party shall...
Sub-Contractor Collateral Warranty in Favour of a Beneficiary with optional step in rightsThis Deed is made on [insert date] day of [insert month]...
Consultant form of collateral warranty to employer (post novation)Date [insert date] 20[insert year]Parties1[insert name of Consultant] (Company...
Consultant form of collateral warranty (with optional step-in clauses)Date [insert date] 20[insert year]Parties1[insert name of Consultant] (Company...
Contractor form of collateral warranty (with optional step-in clauses)This Deed is made on [insert date] day of [insert month] 20[insert...
What is a variation on a construction project?A variation (sometimes referred to as a change) is an alteration to the scope of work originally...
Escrow accounts and escrow agreementsThis Practice Note examines why parties involved in a construction project may enter into an escrow agreement (or...
Defects liability period and rectification of defectsIt is common in construction projects for defects to manifest or appear in the works. Most...
What is practical completion?Practical completion marks the end of the construction period of a project, when the works are 'finished' and the...
Build Operate Transfer (BOT) contractsThe Public Private Partnership (PPP) models are a popular way for governments to involve private investment,...
Differences between adjudication and other forms of dispute resolutionThis Practice Note identifies some of the key differences between adjudication...
Liquidated damages in construction contractsThis Practice Note explains what liquidated and ascertained damages (LADs/LDs) are and their purpose in a...
Time at large in construction contractsThis Practice Note examines the concept of ‘time at large’ in relation to the completion of works under a...
Provisional sumsWhat are provisional sums?There is no precise standard definition of provisional sum but it is generally understood to refer to an...
Scott Schedules in construction disputesScott Schedules are often very useful in construction disputes. They help to identify the key issues between...
The final account in construction and engineering contractsWhat is the final account?The expression 'final account' refers to the consolidated...
Fluctuations in construction contractsWhat are fluctuations?Fluctuations provisions are clauses in construction contracts that allow the contract sum...
Breach of natural justice in adjudicationProduced in association with 4 Pump CourtPrinciples of natural justiceIf an adjudicator breaches the rules of...
New home warrantiesThis Practice Note looks at the principal types of policy or guarantee (other than latent defects insurance) that are currently on...
Extensions of time under construction contractsThis Practice Note examines the circumstances in which a construction contract might entitle a...
A global claim is one where a contractor has suffered loss caused by two or more different events which are employer risk events, but a contractor is unable or unwilling to identify the loss or delay caused by each individual event. Therefore there is one claim for all of the losses arising out of the various events.
New Engineering Contract (NEC) is an industry standard form devised by the NEC group which produces a standard form of contract known as the NEC 3 for the most recent editions.
A schedule usually contained in a consultant’s appointment or pre-construction services agreement and which sets out, in detail, all the services to be performed by the consultant or contractor under the relevant agreement.